FLOODING: TAYLOR BROOK BRIDGE

In 2017, TPA commissioned an engineering study of water levels and flooding issues on Taylor Pond.  The study concluded that removing obstructions to the free flow of Taylor Brook under Hotel Road and Stevens Mill Extension could reduce the chance of flooding on the pond.  In 2019 Maine Department of Transportation (DOT) made plans to improve the Hotel Road culvert, but the project has been delayed (more than once) due to escalation of project costs. The project is currently in the DOT work plan for construction in 2021, an unfortunate delay.
The good news is, once done it will reduce the chance of flooding. Instead of a limited culvert, this will be a bridge that allows water to pass freely down and fish to swim upriver.  Research shows this is better environmentally and cost wise. It is more expensive to construct initially, but requires less maintenance and should have a much longer lifespan than a culvert.

Flooded home on Taylor Pond after hurricane Sandy.